Gas Piping
Gas Piping
Start
Congratulations - you have completed Gas Piping.
You scored %%SCORE%% out of %%TOTAL%%.
Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1 |
A drip leg should be installed
A | On the vertical gas line |
B | On a horizontal line |
C | Before the main gas shutoff |
D | At the gas meter |
Question 2 |
A manual gas cock valve shutoff should be installed at which part of the furnace?
A | Internal |
B | External |
C | At the main gas valve |
D | At the gas meter |
Question 3 |
A common pressure of ________WC is needed from the meter to the furnace when using natural gas.
A | 3.5 |
B | 9” |
C | 7” |
D | 11” |
Question 4 |
A common pressure of________ WC is needed from the gas regulator to the burner orifices for natural gas.
A | 3.5” |
B | 9” |
C | 7” |
D | 11” |
Question 5 |
Liquefied petroleum gas (LPG) must maintain a pressure of_________WC from the regulator at the tank when it is being used
A | 3.5” |
B | 9” |
C | 7”
|
D | 11” |
Question 6 |
______________refers to the relative weight of a gas as compared to the weight of an equal amount of air.
A | Specific gravity |
B | Relative humidity |
C | Specific heat |
D | Density |
Question 7 |
The specific gravity of natural gas is approximately
A | 0.25 |
B | 0.65 |
C | 0.75 |
D | 2.01 |
Question 8 |
To install or alter fuel gas piping
A | A license is always required to obtain a permit |
B | A permit is required by most municipalities |
C | A permit is not required by must municipalities |
D | None of the above are true |
Question 9 |
The gas supply line to a mobile home is commonly
A | ¾” |
B | ½” |
C | 1” |
D | 1 ¼” |
Question 10 |
The gas piping to supply mobile homes should be installed
A | At least 10” below grade |
B | At least 12” below grade |
C | At least 18” below grade |
D | At least 16” below grade |
Question 11 |
When installing gas pipe near structures such as porches, steps, breezeways, etc. gas pipe installations should be kept at least
A | 4” above grade or structure |
B | 6” above grade or structure |
C | 8” above grade or structure |
D | 16” above grade or structure |
Question 12 |
All gas piping must be
A | Vacuum tested |
B | Tested with CO2 |
C | Tested with air pressure |
D | Tested with oxygen |
Question 13 |
Gas piping is commonly constructed of
A | Wrought iron |
B | Steel |
C | Black pipe |
D | All of the above |
Question 14 |
Gas piping that is not protected can be
A | At least 10” below grade |
B | Embedded in 4” of cement |
C | Embedded in 6” of cement |
D | Installed above grade in recesses or channels that are approved |
Question 15 |
Gas shutoff valves should be installed
A | 6’ above floor level |
B | 8’ above floor level |
C | On a horizontal pipe |
D | Within 3’ of the appliance |
Question 16 |
Leaks in gas piping should be located with
A | Nitrogen |
B | Oxygen |
C | A halide torch |
D | A soapy solution |
Question 17 |
All manual gas cock valves need to be
A | Constructed of brass |
B | Approved for gas fuel only |
C | Constructed of aluminum casting |
D | Approved by GAMA |
Question 18 |
Never use an open flame
A | While using a soap solution |
B | To locate gas leaks |
C | Around an electronic leak detector |
D | Around a combustible leak detector |
Question 19 |
Plastic gas piping should be
A | At least 18” below grade |
B | At least 10” below grade |
C | At least 12” below grade |
D | At least 14” below grade |
Question 20 |
Supports for hanging gas piping should be constructed of
A | Plastic straps |
B | Thin wire |
C | Copper hooks |
D | Metal straps or hooks at approved intervals |
Question 21 |
Underground gas piping that is ferrous and metallic should be at least
A | 6” below grade |
B | 8” below grade |
C | 10” below grade |
D | 12” below grade |
Question 22 |
Underground piping should be supported by
A | Compacted soil or sand |
B | Concrete |
C | Top soil |
D | Gravel and soil |
Question 23 |
Black iron pipe is used in areas where corrosion will not effect it, and the elements, and the elements that give the pipe its color is:
A | Copper |
B | Carbon |
C | Silver |
D | The heat treating process gives the pipe its color |
Question 24 |
When measuring black iron pipe, it is measured by its:
A | Outside diameter |
B | Amount of threads per inch |
C | Outside diameter and length |
D | Nominal size |
Question 25 |
A description of nominal size would be:
A |
Outside diameter and length
|
B | Amount of threads per inch and diameter |
C | An approximation of inside diameter for pipe up to 12" in length |
D | An estimation of pipe weight per linear feet |
Question 26 |
Pipe threads type are taper and straight and are classified by:
A | SMACNA
|
B | ACCA |
C | BOCA Code |
D | NPT |
Question 27 |
Pipe thread compound is used on pipe threads for the purpose of:
A | Acting as a lubricant |
B | Protecting the threads from corrosion |
C | Acting as a lubricant and providing a seal |
D | Protecting against contaminants within the gas |
Once you are finished, click the button below. Any items you have not completed will be marked incorrect.
Get Results
There are 27 questions to complete.
← |
List |
→ |
Return
Shaded items are complete.
1 | 2 | 3 | 4 | 5 |
6 | 7 | 8 | 9 | 10 |
11 | 12 | 13 | 14 | 15 |
16 | 17 | 18 | 19 | 20 |
21 | 22 | 23 | 24 | 25 |
26 | 27 | End |
Return
You have completed
questions
question
Your score is
Correct
Wrong
Partial-Credit
You have not finished your quiz. If you leave this page, your progress will be lost.
Correct Answer
You Selected
Not Attempted
Final Score on Quiz
Attempted Questions Correct
Attempted Questions Wrong
Questions Not Attempted
Total Questions on Quiz
Question Details
Results
Date
Score
Hint
Time allowed
minutes
seconds
Time used
Answer Choice(s) Selected
Question Text
All done
Need more practice!
Keep trying!
Not bad!
Good work!
Perfect!